← Back

ZOLUXPRO · CNC

Cost per good part and target batch

EUR estimate with one fixed setup per batch and variable cost per attempt. This is not a selling-price calculator.

Base cost per part without rejects€14.03Cost per good part including rejects€14.40Total target-batch cost€359.98
C = V / (1 − r) + S / Q

Interpreting the estimate

EUR estimate with one fixed setup per batch and variable cost per attempt. This is not a selling-price calculator.

Q is the target number of good parts. V = cycle × rate / 60 + material; S = setup × rate / 60; r = reject rate / 100. Each reject consumes a full cycle and material allowance here, without recovery or rework. Setup occurs once per batch and is not repeated for every reject. Q / (1 − r) is an expected number of attempts, not guaranteed actual output.

Teaching example: cycle 6 min, rate 60 EUR/h, material 2 EUR, setup 60 min, target 10 good parts and rejects 50%. V = 8 EUR and S = 60 EUR; base cost 14 EUR/part, adjusted cost 22 EUR/part and batch 220 EUR. These are not observed costs.

Use the same rate for cycle and setup only where appropriate. Add items absent from the rate, such as labor, tooling, inspection, energy or overhead, without double counting. Tax, margin, salvage value, rework and additional setups are excluded. Validate the model before quoting.

Boothroyd Dewhurst · Machining cost components