Separate cutting, auxiliary movements, handling, inspection and setup without double counting.
A cutting formula covers a defined path under stated conditions. Delivery planning also needs auxiliary motion, handling, inspection and setup. Mixing these quantities can underestimate time or count the same work twice.
One pass at constant RPM
For longitudinal turning at constant feed per revolution, t = L ÷ (f × n): L in mm, f in mm/rev, n in rpm, t in minutes. L is the travel actually made at that feed; include approaches only if they use the same conditions. Worked example: L = 120 mm, f = 0.20 mm/rev, n = 1000 rpm. Linear feed is 200 mm/min; one pass takes 0.60 min or 36 seconds. Four identical passes take 2.40 min. They are equivalent only with the same path and parameters. In G96 facing, RPM changes with diameter and may reach the spindle ceiling; a single-RPM estimate is an approximation that must be identified.
From cutting time to machine time
Assume tool changes, returns and other machine actions add 1.20 min per part, not already included in cutting time: machine time is 2.40 + 1.20 = 3.60 min. A complete timed machine cycle already includes its auxiliary actions; do not add them twice. Loading, unloading and measurement add elapsed time only insofar as they delay the next start. Inspection of the previous part may overlap the automatic cycle. Record the overlap and the portion that actually extends the sequence.
A complete batch example
With setup 45 min, machine time 3.60 min/part and additional non-overlapping time 1.20 min/part, 20 parts take 45 + 20 × (3.60 + 1.20) = 141 min, or 2 h 21 min, before unmodelled waits or incidents. Setup allocation is 45 ÷ 20 = 2.25 min/part; average including setup is 141 ÷ 20 = 7.05 min/part. For five parts with the same assumptions: 69 min and 13.80 min/part. These are constructed scenarios, not measured workshop productivity. The preparation sheet uses these example values; replace them with your own.
Time cost is not a selling price
At an assumed rate of 50 EUR/h, 141 min represents 117.50 EUR, or 5.875 EUR/part. This is not a selling price. Define what the rate includes and what remains: material, tools, scrap, external services and margin. If the rate includes an operator, adding the same labor again duplicates it. An operator serving several machines needs a specific occupancy model. The simple ZoluxPro cost calculator organizes an estimate; a quotation requires validated assumptions.
Compare the estimate with production
Measure setup and cycles separately. Time several parts with consistent start and end definitions, log incidents and do not present an exceptional interruption as the normal cycle. Preserve variation as well as the average. If observed time is longer, locate the changed segment before altering cutting data. On short batches, reducing setup may matter more than saving seconds on one pass. Every parameter change requires checking tool, material, clamping and process.